Penspen entered an engineer, procure and construct (EPC) contract with Spalding Energy to deliver a working gas pipeline system to deliver fuel gas to a new 800 MW CCGT power plant at Spalding. Penspen provided the engineering and procurement services and employed a pipeline construction contractor to build the pipeline and its above ground installations. Penspen provided total project management and construction management of the construction contractor.
The project comprised a gas offtake facility from the National Transmission System, a 7.3 km buried pipeline with a design pressure of 79.5 barg and a pressure reduction and metering station at the power plant. Other facilities include: