The ADCOP project will transport up to 1.8MMBPD of crude oil from the main producing areas in Abu Dhabi to Fujairah on the East coast of the UAE. The project facilities include a 370km long, 48" diameter oil export pipeline
Detailed Design
Sonangol has contracted Penspen to carry out the Design Audit for the Barra Do Dande Oceanic Terminal in Angola. The Oceanic Terminal, which will include new and improved fuel storage and loading facilities, will make up a large part of the new green field port of Barra Do Dande, set to be one of the largest commercial ports in Africa.
Detailed Design | FEED
Assuring the Integrity and Reliability of the Transportation of Hydrocarbons System 1 – in the Tabasco and Campeche areas of the Gulf of Mexico
Integrity
The Greece-Italy Natural Gas Interconnector is a 580 km and 42" diameter high pressure natural gas pipeline from Kotomini in Eastern Greece to Thesprotia in Western Greece.
FEED
Salt cavity storage project including 38km gas pipeline, 19km brine pipeline, gas dehydration facilities, gas compressors and general treatment facilities
Feasibility | FEED | Project Management
Project management of development of crude oil and natural gas pipeline and facilities; new and renovation of the existing
Project Management
New fuel storage tanks and new road loading and pipeline distribution terminal on the existing Buncefield site at Hemel Hempstead in Hertfordshire, UK. Client: Total UK Limited
FEED
Shell U.K. Limited (Shell) is planning the development of the remaining small gas opportunities within its Southern North Sea portfolio, spread over both the UK and Dutch sectors. The development of these gas prospects is commonly known as the SWEEP Project. Low cost subsea system solutions are essential in order to make the development of these gas pockets economically viable
FEED
The anchor of a large oil tanker snagged the buried CATS natural gas pipeline, displacing it several meters, damaging the concrete coating and denting the pipe surface. Penspen was appointed to assist BP with assessing the severity of the damage caused and advising on safe pressures, inspection, and repair.
Integrity
Project Management Consultancy Services for the installation of a new Gas Booster Station at Jabung on the 28" dia 468 km Grissik to Singapore pipeline
FEED | Project Management
The development for the L09 Area development consisted of two platforms L09-FA and L09-FB, evacuating well fluids via one pipeline to the existing host facility L09-FF
Detailed Design
Austria, Bulgaria, Hungary, Romania, Turkey
The Nabucco natural gas pipeline constitutes a dedicated gas transit and transportation pipeline from Turkey to Austria via Bulgaria, Romania and Hungary. Total length is more than 3000 km.
FEED | Project Management
Provide Project Management Services on development of the Greek natural gas pipeline system in mountainous areas. The services cover management of 28 separate projects partially funded under EU community support
Project Management
Turkmenistan, Afghanistan, Pakistan
Techno-economic feasibility of a $2.5bn, 1700km long 56" international gas pipeline project from Turkmenistan to markets in Afghanistan, Pakistan and India. Very high montainous area with high seismicity
Feasibility
Penspen provided guidance to enable the Caspian Pipeline Consortium (CPC) select the best option for the future of the Tengiz to KP116 section of a 1500km pipeline between Tengiz and Novorossiysk, given the risks posed by external corrosion.
Integrity
The first phase of the Gendalo Field development project, part of the giant deepwater Gendalo-Gandang gas field complex offshore East Kalimantan Indonesia. It is proposed that the Gendalo field will be developed utilising, initially, three drill centres with subsea wells in up to 5500 feet sea water (fsw) tied back to a statically moored Floating, Production, Storage and Offloading (FPSO) vessel in 3700 fsw. Processed gas will be exported to the beach
Concept
Development of aviation fuel depot and supply system for new airport
Concept | FEED
PMC services for the EPC and Commissioning of a 185km 36" & 270km, 32" diameter gas transmission pipeline from Conoco Philips gas fields to PLN's power plants in West Java. Mountainous area with rainforest
FEED | Project Management
The project scope includes 150km high pressure pipeline 18" in diameter, plus block valve installations and telecommunications infrastructure. The pipeline will provide security of supply to both Northern Ireland and the Republic of Ireland by linking Interconnectors 1 and 2 to the Scotland Northern Ireland Pipeline (SNIP). The pipeline would also make gas available to towns en-route including Newry, Armagh, Banbridge, Portadown, Lurgan, and Antrim
FEED | Project Management
Techno-economic feasibility study of a 4300km natural gas pipeline from Nigeria to Algeria. The pipeline route includes rainforest, swamps and desert
Feasibility
|