 |
Detailed design of British
Gas Blake Development including subsea manifold. |
With a depth of experience in designing
flowlines and subsea structures, APA was awarded the design
contract for this prestigious development, located in the
South Halibut Basin 60 miles north of St Fergus, by lead contractor
Coflexip Stena Offshore Limited (CSOL).The centrepiece of
the seabed structure, which has a capacity of 40,000 barrels
of crude oil a day, is a 200 tonne manifold and control system
which governs and connects eight subsea production wells.
The manifold incorporates two subsea multiphase flow measuring
devices and will be linked to Talisman's production storage
and off-loading vessel Bleo Holm.

During the challenging 16 week schedule,
APA prepared the full 'Approved for Construction' package for
the Blake manifold which allowed the client to obtain complete
and accurate tenders from fabrication contractors. An essential
part of the design process was the use of 3D modelling which
ensured that the structure's components didn't clash - which
can and does occur if the structure is designed in 2D.
The Aberdeen-based APA project team optimised the structure
layout ensuring it was as compact as possible whilst still meeting
functional requirements. The structural design incorporated
stringent protection requirements against potential damage from
fishing gear and dropped objects.
Production pipelines connecting the
manifold and Bleo Holm consist of a 10 inch inside a 16 inch
'pipe-in-pipe' insulated oil pipeline and a 12 inch pipeline
coated with a thick layer of insulation. In addition there is
a 12 inch, plastic lined pipeline for injecting water into the
oil reservoir and a 6 inch gas lift pipeline for providing gas
to oil producing wells to improve performance. APA prepared
the detailed design of the pipelines for their hydrotest and
operational design conditions taking account of the client's
preferred method of installation, the reeling method.
All aspects of the design were covered
including optimisation of the wall thickness and pipeline stability
and calculation of the amount of rock-dump or soil backfill
required to mitigate the potential for the pipelines to buckle
during test or operation.
APA's design work confirmed that the
proposed pipe-in-pipe system and insulation coatings ensured
the production fluids reached the Bleo Holm at the necessary
temperature to be compatible with the FPSO's production processes
and to ensure the product remained in the optimum condition
for flow in the pipelines.