
The rapid gravity filters looking
over the top of the contact tank.
The objectives of the project were to increase
both the capacity and efficiency of the Caroni Plant which
supplies 80% of Trinidad's water. This was achieved through
a major expansion adding 70 million litres per day capacity,
and also through repairs and upgrades to the existing Plant
structure and equipment.
The scope of the upgrade works included
a new parallel water treatment stream, replacement of raw
water pumps, export pumps, interconnecting pipework, electrical
supply equipment, chemical dosing and instrumentation and
control systems.
The project was awarded to Penspen in competitive
tender against other contractors from both the United States
and Europe. Chris Williams, Director Contracting said:
"Our bid was technically very strong and demonstrated our
ability to provide the works in accordance with the client's
detailed requirements. What won us the job was our ability
to co-ordinate local subcontractors and international equipment
suppliers to give the client a best cost solution."
The contract was subject to extremely challenging
schedule constraints and the works were commissioned within
15 months of contract award. This fast-track programme was
necessary to meet the requirements of the overall upgrade
programme for Trinidad water supply.

The top of the rapid gravity filters
with the export pumping station.
The Penspen project management was the
key feature of the contract and included detailed planning
and cost control, in addition to management of all design,
procurement, construction and commissioning activities. In
particular, the management and expediting of equipment suppliers
to achieve the required delivery dates on site played a major
role in the project success.
Chris Williams paid tribute to the
Penspen project team and said: "This was the first time that
we have worked in Trinidad and the first water treatment plant
project that we have built under a full EPC contract. On both
counts it proved a great success and demonstrates our ability
to deliver projects of this size anywhere in the world within
budget and on time."