
Preparing
to Tie-in.
The TSEP pipeline will transport ethylene
from the Huntsman-ICI Wilton works on Teesside to the new
BP Chemicals ethylene by-products plant at Saltend Chemical
Works near Hull. This extension to the UK Ethylene Network
will provide a reliable and economic supply of ethylene to
the Saltend facility to allow further investment in chemical
production at the Hull site. It will also combine BP's assets
in the North East of the UK into a single 'virtual' site.
Penspen has already designed all of the existing major pipelines
in the UK Ethylene Network which totals over 1000 km in length.
The Network comprises; the BP Mossmorran to Grangemouth pipeline,
the Shell North Western Ethylene Pipeline (NWEP) from Grangemouth
to Stanlow, the BP/Huntsman-ICI Wilton to Grangemouth Ethylene
Pipeline (WGEP) and the Huntsman-ICI Trans-Pennine Ethylene
Pipeline (TPEP) linking Wilton to Stanlow.
Penspen's extensive experience made them
the favoured consultancy for the design work necessary for
the 153km long TSEP development. Penspen was initially appointed
to review the preliminary pipeline route options and prepare
the 1:10,000 route plans and land referencing details.

Main
Laying Crew.
Following a competitive tendering process
in 1998, BP Chemicals formed an alliance agreement with Penspen
Limited undertaking detailed design and the role of Planning
Supervisor, and Murphy Pipelines Ltd undertaking the construction
and installation of the pipeline, civil and mechanical works.
Construction of the pipeline was scheduled over two seasons
with final completion required in time for the proposed commissioning
of the new Saltend ethylene by-products plant in January 2001.
The pipeline affected some 350 landowners,
many different and important archaeological sites, 10 valve
station sites including offtake and terminal sites, 100 road
crossings, 5 rail crossings, 33 river and stream crossings
and 17 Horizontal Directional Drills were designed and installed.
The Alliance was the first of its kind
for a pipeline project in the UK. Penspen's Project Manager,
Alan Marchant, commented: "The Alliance called for a great
deal of mutual trust and co-operation between the three parties
for this complex project. Effective management and highly-motivated
personnel delivering an excellent product installed with the
least possible environmental impact, within the programmed
schedule and with a record breaking safety record for pipelines,
all contributed to the success of TSEP".

Front
End Welding.
Penspen was also awarded an additional
contract for the design, procurement and management of the
Electrical, Control and Instrumentation (EC&I) works associated
with the TSEP project. The EC&I scope included the SCADA system
which was procured following a comprehensive pre-qualification
and evaluation process involving Penspen and BP control personnel.
In order to minimise installation works on site, the Coriolis
meters were incorporated into single skid units fabricated
by an experienced vendor. Penspen placed a subcontract for
the installation of cables and field instruments and supervised
the works in time for commissioning in November 2000.
Peter Skelley, BP's Overseas Manager said:
"Penspen delivered its portions of the works within the budgeted
costs and provided a high level of site design support as
the project progressed. Their previous experience in ethylene
pipelines proved to be invaluable."